<aside>

Catch Up Quick

A town of fewer than 6,000 people is being rushed to approve one of its largest construction projects ever, on ground that HHA says requires engineered improvement and specialised foundations.

The only publicly reported price tag, about $220 million, belongs to an earlier 315 unit concept. HHA has not published an updated total for the current phased plan. Hudson carries planning, service, and execution risks, but the applicant has not published a municipal fiscal impact analysis.

Why it matters: The same rush-and-shame routine has failed here twice since 2024. Some officials use public housing residents' real hardship to bend the rules and cast anyone who asks hard questions as the enemy.

</aside>


<aside>

The Briefing Box:


“And every one that heareth these sayings of mine, and doeth them not, shall be likened unto a foolish man, which built his house upon the sand: And the rain descended, and the floods came, and the winds blew, and beat upon that house; and it fell: and great was the fall of it.”

Matthew 7:26-27

In Hudson, the sand is clay. The flood risk is already on the record.

The Planning Board holds a public hearing on Bliss 2.0 this week: a proposed redevelopment of approximately 266 apartments across several parcels, including land where an earlier HHA proposal encountered serious soil constraints. HHA has not published an updated total cost for the revised plan. Hudson has run this show twice already. Both times it has ended the same way.


The TV Show Formula

Hudson keeps greenlighting the same show. It has a formula, four beats an episode, and reality cancels it every time. Then the city renews it for another season.

Hudson has two settings for a bad idea: greenlight and gaslight.

  1. The rush. An important vote is forced onto a short clock, before the homework is done.
  2. The get-out-of-jail-free card: “Community Care.” A story of compassion, real suffering, urgent need, is played to skip the rules, the eligibility test and the legal process. Ask a hard question and you are recast as cruel.
  3. The compassion shield. The residents’ genuine suffering is raised to drown out the handful of officials who actually read the law. Question the plan and you are cast as the enemy of the people it claims to help.
  4. The predictable finale. What the dissenters warned about happens, on schedule. You saw it coming from the cold open.

The story is not one bad vote. It is the show, made into re-runs. Three episodes, all recent, from 2024 to 2026, and there are almost certainly earlier ones, including during the COVID-19 years, that deserve their own accounting. One grant effort was abandoned. The Mill Street litigation remains unresolved. The third reaches its public hearing this Tuesday.